It’s one of the most common fears a housing society committee raises when redevelopment first comes up, and it’s not an irrational one: what actually happens if the developer we choose runs out of money, or simply walks away, halfway through construction? Members have already vacated, the old building is demolished, and a half-built structure sits where their homes used to be. This article looks at what protections genuinely exist, and — just as importantly — what to insist on before signing so this scenario is survivable rather than catastrophic.
Is your society considering redevelopment? Get a free first assessment of your plot from Mungekar Realty: what it can support, which regulation applies and what to watch out for. The society pays us nothing. Register your property or WhatsApp us on +91 98207 44734.
The uncomfortable truth about RERA here
Many societies assume RERA automatically protects them the way it protects a flat buyer purchasing directly from a developer. In practice, this hasn’t held up cleanly. MahaRERA has previously taken the position that disputes between a society and its chosen developer, on the redevelopment (rehabilitation) side of a project, are a matter between the society, its managing committee, and the developer — not something RERA’s authority is designed to adjudicate. Over 85% of Mumbai’s construction activity now involves redevelopment, and RERA orders have specifically noted that societies need to protect themselves through the terms of their own agreement, not assume the Act will step in on their behalf if a redeveloper defaults on the rehabilitation component. This makes the Development Agreement itself, not RERA, your primary line of defence.
The bank guarantee: your single most important protection
The Government Resolution of 4 July 2019 required developers to furnish a bank guarantee equal to 20% of the total redevelopment project cost. The new GR issued by the Co-operation Department on 30 September 2026 replaces that rule: the society’s general body now decides the amount and form of the bank guarantee. This gives societies flexibility, but it also places the responsibility on members to make sure the guarantee is genuinely adequate, and 20% of project cost remains a sensible minimum to start from. Experienced advisors increasingly recommend going further: a bank guarantee covering 110% of the rehabilitation construction cost, from a scheduled commercial bank (SBI, HDFC, ICICI, Axis, Kotak, and similar), rather than a smaller cooperative bank guarantee, which carries meaningfully less security. This guarantee should specifically cover both the cost of completing rehabilitation construction and the ongoing rent payments to members, with an additional buffer of a few months built in. Without an adequate bank guarantee, if a developer becomes insolvent mid-project, the society is left with a half-finished building, no construction funds, and effectively no recourse, which is precisely the scenario a bank guarantee exists to prevent.
RERA registration still matters, just not as a silver bullet
Projects above a certain size threshold (broadly, more than eight apartments or over 500 square metres of land) must register with MahaRERA, and this registration does provide real value: it forces public disclosure of timelines, requires 70% of amounts collected from free-sale flat buyers to sit in an escrow account released only against certified construction progress, and creates a paper trail regulators and courts can point to. What it does not reliably do, based on how MahaRERA has ruled on society-versus-developer disputes to date, is give your society a direct, guaranteed forum to force a defaulting developer back to the table on the rehabilitation side. Treat RERA registration as one layer of protection among several, not the whole safety net.
What the Development Agreement should explicitly address
Beyond the bank guarantee, a well-drafted agreement should specify: a lien or charge in the society’s favour over the developer’s rights in the property until rehabilitation is complete, so the developer cannot sell the free-sale component and simply disappear with the proceeds while rehabilitation sits unfinished; a clear, enforceable process for what happens if construction stops for a defined period (say, six months) without justification — including the society’s right to terminate the agreement and bring in a replacement developer; and a completion-deadline penalty clause, commonly 5-10% of the new flat’s value per year of delay, paid directly to members, so that delay carries a real cost to the developer rather than being cost-free.
If a project does stall: the practical options
When a developer does become insolvent or simply stops work, a society’s realistic paths forward are: invoking the bank guarantee (if one exists and was properly structured) to fund completion through a replacement contractor or PMC; pursuing the developer through the National Company Law Tribunal if formal insolvency proceedings are underway, though this is typically a long process and rehabilitation-flat claims can be treated with lower priority than other creditors; approaching the Deputy Registrar of Cooperative Societies, since the redevelopment relationship runs through cooperative society law as much as property law; and, in genuinely stuck cases, exploring whether MHADA or another authority has a mechanism to take over a stalled project — a route that has been actively discussed in recent policy circles, though it isn’t yet a routine, fast option for every stalled project.
Prevention is far cheaper than any of these remedies
Every one of the recovery options above involves years and real cost. The much better position is not having to use them at all — which means developer selection, before signing anything, is where this risk is actually managed. A developer’s financial strength, existing debt load, number of other ongoing projects, and track record of finishing (not just starting) redevelopment work are the things worth scrutinising hardest, well before terms like corpus and carpet area even enter the conversation.
How we help societies manage this risk
At Mungekar Realty, screening for exactly this risk — a developer’s genuine financial capacity to complete a project, not just their pitch — is a core part of how we help societies evaluate proposals, alongside making sure the bank guarantee, lien, and default clauses in the Development Agreement are actually adequate rather than boilerplate. If your society is choosing between developer proposals and wants an independent check on this specific risk before signing, we’re happy to help.