Of all the questions a housing society asks when it first considers redevelopment, “how long will this take?” comes up before almost anything else. The honest answer is that it depends heavily on society consensus, plot complexity, and how smoothly approvals move — but most Mumbai redevelopment projects follow a recognisable sequence of stages, each with its own realistic timeline.
Is your society considering redevelopment? Get a free first assessment of your plot from Mungekar Realty: what it can support, which regulation applies and what to watch out for. The society pays us nothing. Register your property or WhatsApp us on +91 98207 44734.
Stage 1: Society Formation and Preliminary Decision (3–6 months)
Before anything else, the society needs to pass a resolution to explore redevelopment, typically at a general body meeting with the required majority. Where the society isn’t properly registered or its membership records are outdated, this stage can stretch considerably as these issues get resolved first.
Stage 2: Consultant Appointment and Feasibility Study (1–2 months)
Once the society decides to proceed, appointing a PMC or redevelopment consultant to prepare a feasibility report is the next step. This report — covering FSI/TDR potential, likely carpet area for members, corpus and rent estimates, and financial viability — typically takes four to eight weeks depending on how quickly property documents and society records are made available.
Stage 3: Developer Selection (3–6 months)
Inviting tenders, evaluating developer proposals, negotiating terms, and securing the required member consent (typically 51% or higher under the relevant scheme) is often the most drawn-out stage. Societies that rush developer selection to save time frequently pay for it later in disputes, so this stage is worth doing thoroughly rather than quickly.
Stage 4: Statutory Approvals (6–12 months, sometimes longer)
This is the stage with the widest variance. IOD, environmental and fire NOCs, plan approvals, RERA registration, and Commencement Certificate all have to be obtained, and delays at any single authority can push the whole stage well past a year — especially where the plot has any title, tenancy, or FSI complications flagged during due diligence.
Stage 5: Construction (24–36 months)
For a typical mid-sized residential redevelopment, construction itself runs two to three years from Commencement Certificate to completion, depending on the number of floors, structural complexity, and the developer’s execution capacity and funding position.
Stage 6: Occupation Certificate, Possession and Conveyance (2–4 months)
After construction, obtaining the Occupation Certificate, handing over flats to members, and executing the conveyance deed in the new society’s favour typically adds a few more months — longer if documentation or society registration formalities weren’t kept current through the project.
So, Realistically, How Long?
Start to finish, most Mumbai redevelopment projects take somewhere between four and six years. Projects that stay on the shorter end usually share three things: a society that reached internal consensus quickly, a developer selected for track record rather than the highest offer, and a feasibility study done early enough to catch FSI, title, or tenancy issues before they become approval-stage surprises.